Agenda item

Minutes:

The report set out the current budget position in respect of the 2018/19 revenue and capital budgets and performance against savings targets. 

 

Revenue Budget

The overall position as at the end of September showed an overspend of £0.3m.  Trends were being monitored to ensure that they were reflected in future years budgets as well as being reported to the Resources Committee.  In terms of the year end forecast, it was still early in the year however, the latest forecast showed an overall underspend of approximately £0.1m, reflecting anticipated vacancies in the second half of the year, the lack of an apprentice FF programme and the timing of some non-pay expenditure.  It was noted that the budget allowed for a 2% July 2017 pay award for grey book personnel, this was actually agreed at 1% hence the budget was overstated by £300k, which was reflected in the position outlined.

 

The Committee was provided with detailed information regarding the position within individual departments, with major variances relating to non-pay spends and variances on the pay budget being shown below:-

 

Area

Overspend/ (Under spend) to 30 Sept

Forecast Outturn at 31 March

Reason

 

£’000

£’000

 

Winter Hill

110

110

Costs agreed to date currently stood at £1m, however it was noted that we were awaiting outstanding invoices in relation to the incident from three FRS who assisted and as such could not accurately predict the final total cost.

As reported previously we intend to submit a claim under the Bellwin Scheme of Emergency Financial Assistance and hence anticipated our total net costs being limited to the threshold £110k.

The Committee would be updated on final costs, once all claims had been received.

Procurement

52

73

The overspend to date and the outturn position both related to the replacement of Personal Protective Equipment which had reached the end of its economic life. In addition the recruitment that had taken place in year had led to an increased spend on Technical Rescue Jackets, to accommodate size changes since the initial bulk purchase prior to roll out.  This had ultimately led to the need to purchase more of the common sizes of jacket in order to hold the correct amount in the pooled stock.  We were currently reviewing pooled PPE stock, which was nearing the end of its life, to determine likely outturn costs as well as on-going budget requirements.

Property

103

150

The overspend position related to premises repairs and maintenance. The forecast overspend reflected some of the new minor schemes approved in year to enhance station facilities such as enhanced female facilities.

Pensions

(13)

80

The outturn position reflected a number of ill health retirements anticipated before the end of the financial year.  This position may alter as exact costs and timings were finalised.

Non DFM

(58)

(174)

The year to date underspend was largely due to the increase in the bank base interest rate during the year, increasing interest receivable on our call account balances with Lancashire County Council.  In addition, the outturn position reflected the above, plus interest receivable on several fixed term investments which had been put in place commencing in the second half of the year.

Wholetime Pay

133

(358)

The following issues affected whole-time pay:

·        The budget allowed for an assumed 2% pay award last year, however this did not transpire, hence in the first six months of the year there had been an underspend of £150k. (With a full year effect of £300k)

·        Overtime was overspent by approx. £60k the majority of which was attributable to the continuing policy of detaching wholetime personnel into key RDS stations.

·        As in previous years the budget included a vacancy factor based on anticipated retirements, leavers and new recruits. During the first four months staffing numbers had been higher than forecast, due to fewer retirements, leading to overspend of approx. £100k. Whilst it was impossible to accurately predict this going forward, we had reviewed the position which was likely to reverse in the second half of the year due to a number of outstanding retirements coupled with several personnel leaving the service early. Hence we anticipate a broadly balanced position in respect of this at the year end.

·        The budget also allowed for the recruitment of 12 FF apprentices in the second half of the year, at a cost of £250k. Given the difficulty in establishing a suitable apprentice’s scheme, as previously reported, it was clear that these would not be recruited until next year, and hence no costs would be incurred.

Retained (RDS) Pay

217

 

377

The following issues affected retained pay:

·        As referred to under whole-time pay the budget allowed for 2% pay awards in both years. Hence in the first six months of the year there had been an underspend of £22k.

·        Activity levels in the first 6 months of the year were higher than previous (excluding Winter Hill), reflecting increased hours of cover as well as an increasing number of incidents and hence pay costs were higher than forecast

·        In addition RDS recruits received wholetime pay during the recruits course for two weeks, resulting in an overspend of £40k due to timing, on the two RDS courses that ran during the first six months

Previously, the significant vacant posts in excess of the budgeted vacancy factor within RDS pay had mitigated any overspends, however with the improvement in retention/recruitment these were  more visible, and would be reviewed for the next financial year’s budget.

Associate Trainers

36

60

The annual training plan was used to match planned training activity to staff available at the training centre.  Where this was not possible, associate trainers were brought in to cover the shortfall.  There had been several ongoing trainer vacancies throughout the year to date, which had resulted in the overspend shown, but were counteracted by corresponding underspends within wholetime pay.

Support staff (less agency staff)

(154)

(259)

The underspend to date related to vacant posts across various departments, which were in excess of the vacancy factor built into the budget. (Note agency staff costs to date of £33k were replacing vacant support staff roles, this still only accounted for less than 1% of total support staff costs).

Although some vacancies had been filled, there were a number of vacancies which had proven historically difficult to fill, most notably in ICT and Information Management, resulting in a forecast outturn underspend of £259k. The Service continued to review roles and structures before moving to recruitment.

Apprentice Levy

(7)

(19)

The apprentice levy was payable at 0.5% of each months’ payroll costs, the budget for this was set at anticipated establishment levels, hence the underspend against this budget reflected the various pay budget positions reported above.

It was noted that due to delays in apprenticeships standards being approved we had not been able to utilise the levy payments we had made to HMRC since April 2017. The outcome of this was that funds that had been in the levy account for 24 months and had not been utilised would be clawed back by HMRC.  Whilst this would not affect the current year it would impact next year. At the present time we anticipated a claw back of  £10k per month until we could fully utilise this for training costs.  We had submitted an application for STC to be an approved training provider, in order to access HMRC levy funds to match training costs, however the timing of the approval process was unknown, hence no such income had been forecast in the current financial year.

 

County Councillor O’Toole queried the Pensions forecast outturn position and asked what the anticipated number of ill health retirements was based on.  The Director of People and Development confirmed that there were very stringent rules on granting ill health retirement and that as he determined eligibility he was aware of a couple of individuals who would qualify.  He advised that the process was long and involved individuals seeing an independent health professional whose decision the Service had to abide by.

 

County Councillor O’Toole queried how Associate Trainer vacancies were filled.  The Director of People and Development advised that there had been recruitment difficulties but the vacancies had now been filled.  He advised that Associate Trainers were used where there was a need for a particular specialism and during peaks of work.

 

In response to a question raised by Councillor Williams regarding whether the Retained Duty System Pay excluded the Winter Hill payments, the Director of Corporate Services advised that all the costs for Winter Hill were excluded as a separate cost centre had been set up.  The current cost stood at £1m with the assumption that £110k would be paid by the Authority and the remaining £890k could be claimed back from government once all costs had been received.  Some outstanding bills were awaited before the end of November in order for us to then make the claim.  The Chief Fire Officer advised that some general principles had been agreed with Manchester to ensure consistency of claims.

 

Capital Budget

The Capital Programme for 2018/19 previously stood at £16.7m however, following the September Resources Committee the programme had been amended to remove the expected slippage as reported, hence the revised programme now stood at £4.1m.  The slippage removed would be brought into the 2019/20 capital programme during the budget setting process as now considered by Members:

 

Heading

Slipped

£m

Reason

Pumping Appliances

1.134

Reflecting the anticipated stage payments in the next financial year as previously reported.

Other Vehicles

0.580

Two Command Support Units (CSU), the requirements were currently being finalised with a view to undertaking a procurement exercise. However taking account of anticipated lead times the final costs associated with the purchase of these, £0.6m, would slip over into 2019/20.

Operational Equipment/Future Firefighting

0.310

£160k in relation to BA radios had been moved to 2019/20.

£150k associated with on-going research projects relating to new equipment had been removed to slip forwards to meet the future costs.

Building Modifications

9.069

Preston Fire Station redevelopment, £6.9m had been moved into 2019/20 in relation to expected spend due to the delays associated with NWAS’ decision not to continue site sharing.

Fleet workshop facility, £2.0m. The replacement Fleet workshop was currently undergoing a detailed design prior to undertaking a tendering exercise, and again had been slipped into 2019/20.

IT systems

1.470

£1.0m related to the national Emergency Services Mobile Communications Project (ESMCP), to replace the Airwave wide area radio system. This national project had suffered lengthy delays to date, and it was likely that the budget would slip into 2019/20, therefore both the budget and associated grant had been moved into 2019/20.

The balance of the slippage related to the replacement of various systems, in line with the ICT asset management plan, where progress to date indicated any eventual spend would be incurred in 2019/20.

Total

12.563

 

 

A review of the remaining programme had been undertaken to identify progress against the schemes.  The overall position as at the end of September showed £2.0m of capital expenditure. The current anticipated year end spend was £4.1m, with zero slippage. This position was shown as set out below, and summarised in appendix 2 as now considered by Members: -

 

Pumping Appliances

The budget allowed for the first stage payment for the 7 pumping appliances ordered for the 2018/19 programme.  The remainder of the budget had been included in the 2019/20 draft programme.

Other vehicles

This budget allowed for the replacement of various operational support vehicles:

·        One Aerial Ladder Platform which was delivered during July; and

·        One Water Tower, which was scheduled for delivery  during the financial year.

·        Various support vehicles which were reviewed prior to replacement. As the lead times on these were relatively short we anticipated utilising this budget in year.

Operational Equipment/Future Firefighting

This budget allowed for the initial purchase of technical rescue jackets, following the regional procurement exercise, which were delivered at the end of May and now in service.

£40k related to the purchase of fist microphones, which included noise cancelling facilities and hence enabled clearer voice transmission, thus aiding fire ground communications.

The balance of £50k was to meet costs associated with on-going research projects relating to new equipment, and we anticipated utilising this in the current year.

Building Modifications

Completion of the new joint Fire & Ambulance facility at Lancaster was completed in October. Contract variations of £41k had been agreed in respect of time delays due to the discharge of planning conditions, and upgrading the appliance bay doors, however there were a further £40k variations still being discussed with the contractors. 

In terms of the redevelopment of Preston Fire Station, the budget allowed for £0.1m of fees which might be incurred before the end of March.

The final element of this capital budget related to the balance of the Training Centre redevelopment works, largely relating to the replacement welfare/ICT porta-cabin which would be progressed before the end of the financial year.

IT systems

Given the delay on the ESMCP project, the replacement station end project had also been delayed. However we could not delay this indefinitely and had therefore commenced work to replace the station end in the current financial year, whilst ensuring that any solution would be compatible with the eventual ESMCP solution.

The budget also allowed for the replacement of the Service’s wide area network (WAN) providing an enhanced network and improving speed of use across the Service, and having agreed a contract for this we anticipated this being completed in the current financial year.

 

 

Expenditure to date had been funded from the on-going revenue contributions, with the majority of the year end forecast also being met by this, supported by capital reserves.

 

Delivery against savings targets

The current position on savings targets identified during the budget setting process was reported.  It was anticipated that we would meet our efficiency target for the financial year.

 

RESOLVED: - That the Committee noted and endorsed the financial position and approved the amendment to the 2018/19 capital budget.

Supporting documents: