Agenda item

Minutes:

A report was presented to the meeting in December requesting Members to give initial consideration to the Capital Programme for 2018/19-2022/23. The draft capital programme had been updated to reflect additional expenditure requirements associated with the replacement of Preston Fire and Ambulance Station. Additionally a lower requirement was being forecast in terms of officer cars than originally anticipated. Allowing for these changes the revised programme stood at £20.9m.

 

A full breakdown of the programme was considered by Members.

 

The majority of the expenditure in the capital programme related to:-

 

  • The on-going vehicle replacement programme;
  • Replacement of operational equipment in line with assets lives;
  • Building projects; and
  • Replacement of ICT equipment in line with the current Asset Management Plan.

 

It was noted that the full cost of schemes was included in the year in which work was anticipated to start.  

 

As presented previously no allowance had been made for the potential relocation of Service Headquarters, as this project was due to be reviewed in 2018/19. The programme as presented would need updating if the Authority decided to pursue the relocation.

 

A further report would be presented to the Resources Committee in June, confirming the final year end capital outturn for 2017/18 and the impact of slippage from this on the programme outlined.

 

A number of vehicles had protracted lead times in excess of 12 months. Therefore in order to deliver vehicles in line with their replacement timeframes it was necessary to order pumping appliances, water towers and Aerial Ladder Platforms (ALP’s) at least 12 months prior to their planned replacement. As such orders in respect of 3 pumping appliances and 1 ALP scheduled for replacement in 2019/20 would need to be ordered in the new financial year.

 

Available Resources

 

The draft capital budget report identified total available funding of £22.4m to be used in the period.

 

The Local Government Finance Settlement did not include any reference to any other future capital grant and hence no allowance has been made for this.

 

The final funding for the programme is set out below:-

 

 

2018/19

2019/20

2020/21

2021/22

2022/23

TOTAL

 

£m

£m

£m

£m

£m

£m

Capital Grant

-

-

-

-

-

-

Capital Receipts

-

-

1.018

0.060

-

1.078

Capital Reserves

5.998

3.811

0.905

-

(0.842)

9.872

Revenue Contributions

2.000

2.000

2.000

2.000

2.000

10.000

Earmarked Reserves

-

-

-

-

-

-

 

7.998

5.811

3.923

2.060

1.158

20.950

 

Summary Position

 

The capital programme breaks even over the 5 year period:-

 

 

2018/19

2019/20

2020/21

2021/22

2022/23

TOTAL

 

£m

£m

£m

£m

£m

£m

Capital Requirements

7.998

5.811

3.923

2.060

1.158

20.950

Capital Funding

7.998

5.811

3.923

2.060

1.158

20.950

Surplus /(Shortfall)

-

-

-

-

-

-

 

The overall programme showed a balanced position and hence the capital programme was considered affordable, prudent and sustainable.

 

Capital Reserves/Receipts

 

The table in the report showed the anticipated movements on both capital reserves and capital receipts during the course of the 5-year programme, showing that at the end of the 5 year programme the Authority would still hold £1.4m which could be used to supplement the revenue contributions in future years, thus providing a sustainable capital position in the medium term

 

Prudential Indicators

 

The Prudential Code gave the Authority increased flexibility over its level of capital investment and much greater freedom to borrow, should this be necessary, to finance planned expenditure.  However, in determining the level of borrowing, the Authority must prepare and take account of a number of Prudential Indicators aimed at demonstrating that the level and method of financing capital expenditure was affordable, prudent and sustainable.  Members considered the Indicators that were set out at Appendix 1 now presented, along with a brief commentary on each. 

 

The main emphasis of these Indicators was to enable the Authority to assess whether its proposed spending and its financing was affordable, prudent and sustainable and in this context, the Treasurer's assessment was that, based on the Indicators, this was the case for the following reasons: -

 

·        In terms of affordability, the negative ratio of financing costs arising from borrowing reflected interest receivable exceeding interest payable and Minimum Revenue Provision payments in each of the three years.  This reflected the effect of the previous decision to set aside monies to repay debt.

·        The estimated impact of the planned spends on the Band D Council Tax was again felt to be within affordable limits. The overall impact on council tax in 2018/19 was £34.05 per Band D property (50% of total council tax). However, all of this arose from the utilisation of capital reserves, which had been charged to council tax in previous years and the revenue contributions to support capital expenditure built into the 2018/19 revenue budget.  The actual impact of the capital programme in terms of new borrowing was £0.00 per band D property (0% of total council tax).

·        In terms of prudence, the level of capital expenditure, in absolute terms, was considered to be prudent and sustainable at an annual average of £8.5m over the 3-year period after allowing for anticipated slippage from 2017/18.  The trend in the capital financing requirement and the level of external debt were both considered to be within prudent and sustainable levels.  No borrowing was planned during the three years.

 

RESOLVED: - That the Authority approved:

 

1.            the Capital Budget;

2.            the order of 3 pumping appliances and 1 ALP, scheduled for replacement in 2019/20, in the new financial year in order to meet delivery timeframes; and

3.            the Prudential Indicators as presented.

Supporting documents: